Pakistan’s state-owned transmission company wins legal battle against Iranian firm

0
827

Corporate Desk
National Transmission and Despatch Company (NTDC) , a subsidiary of Pakistan’s Ministry of Energy (Power Division) has prevailed in an international commercial arbitration initiated by an Iranian company about four years agobefore an arbitral tribunal constituted under the rules of Paris-based International Chamber of Commerce (ICC).
According to a spokesman of NTDC, in its detailed Award released this week, the arbitral tribunal has dismissed all the claims brought by the Iranian company and accepted and granted several counterclaims of NTDC amounting to approximately Rs 714 million ( US$ 4.5 Million) in addition to interest at the rate of 7.925 % per year.
The dispute arose out of a contract between the Iranian company and NTDC executed in February 2011 for the design, supply, installation, testing, and commissioning of 500 kV Guddu-Multan 3rd Circuit at Rahim Yar Khan 500kV substation. NTDC had terminated the contract due to persistent delays on the part of the Iranian contractor and the project was eventually completed by another contractor.
The spokesman said that the Iranian company, GAM ARAK initiated the arbitration in early 2017 claiming an amount of approximately Rs 180 million (US$ 1.1 Million) on account of unpaid invoices and damages. NTDC, apart from defending the claims, had filed its own counterclaims alleging the Iranian company’s delays, the costs required to complete the project from another contractor, and claims related to liquidated damages, mobilization advances, customs duties, and demurrage.
The arbitral tribunal held that NTDC had validly terminated the contract as the Iranian company was responsible for the delay in the project. Accordingly, NTDC was awarded liquidated damages in the amount of JPY 93,591,449 and Rs 57,493,057 to compensate NTDC for the delay in project completion. Furthermore, NTDC was also awarded the amounts of JPY 151,699,145 and Rs 167,546,831 as differential costs in respect of the new contractor engaged by NTDC to complete the project.
The tribunal also ordered the Iranian company to repay NTDC the unadjusted portion of the mobilization advance given to it at the time of the project commencement amounting to JPY 49,830,686 and PKR 12,212,346 and a portion (PKR 28,133,604) of the demurrage charges paid by NTDC when shipments were stuck at port.
The spokesman further said that NTDC is also entitled to interest at the rate of 7.925% per annum for the Pakistani Rupee portion of the damages awarded in its favour. The interest will accrue from 6 July 2018 and run until such time as payment of the award is made. Given NTDC’s near-total success on its counterclaims, the sole arbitrator also awarded NTDC 78% of its legal and other costs in the arbitration.

LEAVE A REPLY

Please enter your comment!
Please enter your name here